Update the Riordan HR Integration Schedule based on feedback.

Closed

File name should have been "Week 2 George"

Project within scope of assignment, though there is duration on the Support

Product task.

You failed to meet the 42 detail task count requirement. 36

Project Start Date properly set.

The Summary Task Name for the Project should reflect the entire project and

be suffixed with Moniker. See Instructor Policies.

Some of your tasks need to be clarified. As stated in the Week 2 welcome,

when developing a schedule, the lowest or work level task must be action

oriented and should consist of a verb and an object.

Some of the tasks do not fit within the Summary. For example, you have

"Perform Vendor Response Requirements Gap Analysis" within "Integration Build

and Test".

The integrated HRIS is being developed in house with contractors that on

board from the previously failed project. Even if there were to be a purchased

product, what is it that the vendors have responded to? See additional

comments within content section.

First, the budget has been determined by Riordan. Riordan management will

review your schedule and based on various criteria, determine whether to accept

the schedule. Your proposed costs would be the cost of the project as

reflected within the schedule.

Second, the schedule needs to reflect the work necessary to develop the

integrated HRIS in house. Tasks need to be expanded to support the analysis,

design, and development of each of the HRIS modules (sub-systems) including

unit testing, integration testing, user testing, development of training, etc.,

as indicated in the feedback of your Statement of Work, which contained no

indication that a package would be procured.

Though all of your tasks are Auto Scheduled, As Soon As Possible, there are

numerous spelling errors, which detract from the quality of the schedule.

See details in the Assignment Tab Attachment

Skills: Microsoft, Project Management

See more: assignment, user testing review, the review board, test review board, tab scope, product design and analysis, object oriented analysis and design, hr project work, development review board, what is object oriented design, week schedule, additional comments, work schedule, riordan, review feedback, integration test, hris, hr training, hr systems, HR management , auto update, integration testing example, assignment based project, schedule management, microsoft project assignment

Project ID: #4407705

3 freelancers are bidding on average $202 for this job

preshitp86

I am working in projects for last 5 years. I am good in project planning phase. I would help you to make a better schedule for your tasks with critical path. I am good in Microsoft projects. I am also certified in Proj More

$220 USD in 5 days
(0 Reviews)
0.0
tpksharma

Hi, i am from mauli services having 6+ years of experience in Project management. Having good experience in project planing with PERT chart technique.

$135 USD in 3 days
(0 Reviews)
0.0
hansnld

I can do this for you when I have tiem next week

$250 USD in 20 days
(0 Reviews)
0.0