Closed

Crystal Ball Analysis - Construction Time

A prestigious university in the Pacific

Northwest is planning to build a new business school building on campus. To accomplish this, the activities

listed in the following table must be completed. For most of these activities there is a set of predecessor

activities that must be completed before the activity begins. For example, the foundation cannot be laid until

the building is designed and the site prepared.

Activity Predecessors

A. Obtain Funding -

B. Design Building A

C. Prepare Site A

D. Lay Foundation B, C

E. Erect Walls and Roof D

F. Finish Exterior E

G. Finish Interior E

H. Landscape Grounds F,G

Obtaining funding will likely take somewhere around 9 months. They estimate about a two-thirds chance that

the time required to obtain funding will be within two months (plus or minus) of this estimate, but there is a

small chance this estimate could be significantly off. The architect has estimated the time required to design

the building is equally likely to be anywhere between 5 and 9 months. The general contractor has provided

three estimates for each of the construction tasks—an optimistic scenario (minimum time required if the

weather is good and all goes well), a most likely scenario, and a pessimistic scenario (maximum time required,

e.g., if there are weather or other problems). These estimates are provided in the table below. Finally, the

landscaper has guaranteed that his work will be completed in 1 month.

Activity Optimistic Most Likely Pessimistic

C. Prepare Site 5 8 10

D. Lay Foundation 3 3.5 4

E. Erect Walls and Roof 6 9 11

F. Finish Exterior 5 7 10

G. Finish Interior 6 7 10

Use Crystal Ball to run a simulation of this project. Please use the following Run Preferences: 2000 Trials,

Use Same Sequence of Random Numbers with an Initial Seed Value of 999, and the Latin Hypercube

Sampling Method with a Sample Size of 500. Use the Set Cell Value to Distribution Mean option under Cell

Preferences. Also, be sure to clearly indicate which cells are assumption cells and which are forecast cells, and

indicate directly on the spreadsheet the distributions and parameters used for each assumption cell. Be sure to

work directly in the provided Excel file. Do not work in a separate spreadsheet and copy your models into

this file—Crystal Ball data do not come through with Excel’s copy and paste.

Answer each of the following questions in a sentence or two. Paste in any Crystal Ball output required for

your analysis. (Use Copy Chart under the Edit menu of the forecast chart window.)

a. What is the expected time (mean) for project completion?

b. They hope to have the building ready for classes in 40 months. What is the probability that the

project will be completed in 40 months or less?

c. Which of the activities would be most important to keep an eye on in order to complete this project

on schedule? Explain.

Skills: Excel

See more: construction time, excel crystal ball paste, crystal ball sentence, optimistic time construction, project time crystal ball, construction crystal ball, work pacific, window schedule sample, window schedule example, schedule anywhere, sampling design, sample window schedule, sample problems, sample probability questions, random distributions, questions probability, probability sample problems, method models, interior design school, interior design architect, good probability questions, eye ball, excel contractor, example problems probability, example probability problems

About the Employer:
( 0 reviews ) United States

Project ID: #1155761

5 freelancers are bidding on average $242 for this job

kenan3t

An experienced data analyst with a huge statistical background and analysis software savvy..

$250 USD in 5 days
(1 Review)
2.5
Paranos

I am a US based consultant with immediate availability to work on your project. I look forward to working with you on this project and would consider this a trial run for future business. See PM for details regards, Pa More

$250 USD in 2 days
(1 Review)
2.1
ausdavid

Hi, I have read your requirements. Let me do this for you. I have the experience needed to solve this problem in excel 2010.

$250 USD in 14 days
(1 Review)
1.0
starhill19

dear sir, i can do this job perfectly. so u will try me. i will wait for your message. thanks

$230 USD in 10 days
(0 Reviews)
0.0
Sohaib680

((((((((((((((((Plz See PM))))))))))))))))))

$230 USD in 1 day
(0 Reviews)
0.0